Scott Stadium Expansion Update
July 7, 2000
CONSTRUCTION PROGRESS The site work, including the fencing and gate structures, is nearing completion and some of the landscaping preparation work and ground cover will commence in July. The major portion of the landscaping will not be installed until the weather cools down in the fall. Some will be in place for the last home game on 18 November.
STADIUM STATISTICS There has been a significant increase in the amount of questions being asked about the Project and what new facilities will be included for the opening this September. Many of these questions have been asked during the various tours on site so this UPDATE contains some of the statistics we are asked about most often. Also included are some construction facts which may be of interest to those in the Engineering, Architectural or Construction fields.
PROJECT FACTS
Old New
Total Capacity 45,000 61,500
Luxury Suites 0 44
President's Box Seats 132 360
President's Box Lounge 2,500 sq. ft. 8,000 sq. ft.
Press Box 3,500 sq. ft. 8,000 sq. ft.
Press Box (Working Press)70 Positions 128 Positions
Concession stands 8 25
Women's Toilets 100 461
Men's Toilets 184 414
Field Light Towers 120 ft high 180 ft. high
Television sets 20 232
BRYANT HALL
Old New
Total Sq. Ft. 30,000 60,000
Home team locker room 1,703 sq. ft. 3,630 sq. ft.
Visitor locker room 1,273 sq. ft. 1,750 sq. ft.
New Football museum 0 3,800 sq. ft.
(Bryant Hall Level II)
PERGOLA (pur'ga-la)
SUITES
PARKING GARAGE
LANDSCAPING
PROJECT CONSTRUCTION FACTS
OTHER INTERESTING FACTS
|